Sampaguita Construction Bulletin - September 2017

Another bloom is on the rise, Sampaguita at Larossa In Capitol Hills. With the ongoing full-blast construction, we are pleased to provide the following updates as of September 2017:

Building Construction Progress: 20.45%

Actual Photos of Sampaguita as of Septmber 19, 2017

Actual Photos of Sampaguita as of Septmber 19, 2017

Construction Highlights & Activities: 
Sampaguita construction is currently up to the 8th floor already. Below are the updated construction per floor:

BASEMENT:

Structural:

b-structural-2.jpg

a. Drilling of pilecap 

b. Clearing and grading

GROUND FLOOR:

Architectural:

g-archi-1.jpg

a. Waterproofing Application

b. Masonry Works

3RD FLOOR:

Structural:

3-structural-1.jpg
 

a. Alignment of precast

7TH FLOOR:

Structural:

7-structural-1.jpg
 

a. Enclosure of forms on shearwall

8TH FLOOR:

Structural:

8-structural-1.jpg

a. Installation of rebars on shearwall

b. Installation of rebars on slab

c. Enclosure of forms on shearwall

Visit our website every month for construction updates. Should you have further inquiries & concerns,  you may contact us at 0917 705 3162. Thank you for your support.