Magnolia Construction Bulletin - September 2017

Another bloom is on the rise, Magnolia at Larossa In Capitol Hills. With the ongoing full-blast construction, we are pleased to provide the following updates as of September 2017:

Building Construction Progress: 23.40%

Actual Photos of Magnolia as of Septmeber 19,2017

Actual Photos of Magnolia as of Septmeber 19,2017

Construction Highlights & Activities: 
Magnolia construction is currently up to the 5th floor already. Below are the updated construction per floor:

GROUND FLOOR:

Architectural:

g-archi-1.jpg

a. Formworks for stiffener and lintel beam

g-archi-2.jpg

b. Scratch coating

3RD FLOOR:

Structural:

3-structural-1.jpg
3-structural-2.jpg

b. Form enclosure

a. Installation of rebar

Electrical:

Mechanical:

3-mechanical-1.jpg
3-electrical-1.jpg

a. Box setting

a. Installation of 150mm pipe sleeves for mechanical exhaust

4TH FLOOR:

Electrical:

Structural:

4-structural-1.jpg
4-electrical-1.jpg

a. Roughing Ins

a. Installation of rebar and forms

5TH FLOOR:

Mechanical:

Structural:

5-structural-1.jpg
5-mechanical-1.jpg

a. Installation of 150mm pipe sleeves for mechanical exhaust

a. Concrete pouring

Visit our website every month for construction updates. Should you have further inquiries & concerns,  you may contact us at 0917 705 3162. Thank you for your support.